NOTICE of WORK - Disruption to Lot Q Access

 

NOTICE of WORK

Please be advised that access to Parking Lot Q will be disrupted due to electrical and data connectivity – coming from B255 and going to the GeoExchange Production Well.

 

Project:

GeoExchange

Type of Work:

Trenching

Reason for Work:

Electrical and data connectivity to the Production Well

Contractor:

CANbuild Solutions/Houle Electric

Location:

West side of B255

Schedule:

Start:   Tuesday June 19, 2018

End:   Friday June 22, 2018

Impact:

Medium/Low

  • The main disruption may be intermittent access to Parking Lot Q. There will be a person on the site to direct traffic and the trenched area will be identified and cordoned off.  The process will be to do half the road then fill/do the other half and fill to mitigate inconvenience. Appropriate safety measures will be taken.
  • Concrete work – Tuesday, June 19, 2018
  • Asphalt Trenching/Excavating/Backfill – Wednesday, June 20-22, 2018

Safety:

Exercise caution around work zones. 

Do not enter cordoned areas and obey all signs & instructions given by construction workers. 

Noise and vibrations may occur during the construction process.

Contact:

VIU Project Manager:

Deb Smilski

250.740.6517

debra.smilski@viu.ca

 

For any questions / comments, please contact the Project Manager listed above.  Thank you in advance for your patience and understanding as we complete this work.

 

Sincerely,

 

Facilities Services & Campus Development

Local: 6500   |   P: 250.740.6500  |    W: www.viu.ca/facilities   |   E: facility@viu.ca

Bldg.120 - 900 Fifth Street, Nanaimo, BC, V9R 5S5   |   M-F  7:30am-3:30pm